Services Portfolio
Recent Projects

DURATION: 90 DAYS
MAGNITUDE : 350 ml of Banks of pipelines of concrete piping, 160mm, 1100 m3 of concrete
DESCRIPTION: consisted of the construction of a bank of pipelines to carry out the ...
Montajes líneas eléctricas espesadores

DURATION: 90 Days
MAGNITUDE: Surface 750 m2, 45,000 kg of metallic structure, 550 m2 of isolated coatings, 800 m2 of isolated cover, 750 m2 of pavements.
DESCRIPTION:It consisted in the ...
Mejoras Campamento 5400

DURATION: 120 days
MAGNITUDE: 300 m3 Concrete Demolition - 50 Ton Structure of unarmed.
DESCRIPTION: Disarmament of the former plant of hydrocyclones plant located in the "Tortolas" Doves ...
Retiro Instalaciones Ex Planta de Hidrociclones, muro principal tranque Las Tórtolas

Modular Building Solutions ASAP
ASAP Integral Solutions has key staff with more than 15 years of experience in the assembly of all types of modular installations in the different geographies and ...
Modular Building Rupanco House

Project Name
Disarm Infiernillo Installation
Customer
Tecno Fast S.A
Location
Los Bronces Mining Camp
Description
The disarmament work carried out consisted basically ...
Disarm Infiernillo Installation

Modular Building Solutions ASAP
ASAP Integral Solutions has key staff with more than 15 years of experience in the assembly of all types of modular installations in the different geographies and ...
Modular Building Solutions

Project Name
New Mining Camp - Los Bronces
Customer
Tecno Fast S.A
Location
Los Bronces Mining Camp
Quantity built
2,400 m3 of land – 12,500 m2 of road improvement.
Description
At ...
New Mining Camp Perez Caldera – Los Bronces

Project Name
Works of link movement of earth dam- Codelco
Customer
Codelco
Location
Tranque Ovejería
Quantity built
2,400 m3 of land – 12,500 m2 of road ...
Works of link movement of earth dam- Codelco

Project Name
Montaje Estructura Madera Laminada Nuevo Complejo Los Libertadores
Location
Los Libertadores Internacional Pass
Period of implementation
2017 -2018
Descripción
The work ...
Assembly structure laminated wood new complex Los Libertadores
Noticias
New headquarters ASAP Group
Between the end of 2016 and 2017 principles we moved to our new Headquarters. With more space for